🌏 INTERNATIONAL ☀️🔋 HYBRID PROJECT ⚡ 100 MW / 200 MWh

GoodPower 6 (GP6)

Large-scale hybrid project in Vientiane, Laos: Up to 100 MW solar energy + 200 MWh battery storage. 35.65 hectares land area. Next phase in GoodPower’s international expansion.

LOCATION
Vientiane
Laos
SOLAR CAPACITY
Up to 100 MW
BATTERY
Up to 200 MWh
LAND AREA
35.65 hectares
Exclusive
GRID CON.
EDL
Électricité du Laos
TECH
BESS + Solar
Hybrid
🎬 VISUAL PRESENTATION

Drone video from the project site

View the project site in Laos from above – 35.65 hectares of land area with strategic location near important infrastructure.

Drone video from the project site in Laos – GoodPower 6

📸 VISUAL MATERIAL

Project Images & Maps

Drone images and strategic maps from the project site in Vientiane, Laos.

Project site in Vientiane, Laos - 35.65 hectare area

Project Site in Laos – Overview

Area: 35.65 hectares (356,494 m²). Approximately 50 km from central Vientiane.

Topography and terrain at project site

Topography and Terrain

Infrastructure and accessibility to project site

Infrastructure and Accessibility

Strategic map - Project location near Nabong substation

Strategic Map – Location

The project is strategically located near the Nabong substation, ensuring optimal grid connection for the solar park and battery storage system.

Strategic advantage: Prime location near key infrastructure ensures maximum efficiency and connectivity.

🌏 GOODPOWER 6 – INTERNATIONAL EXPANSION 🚀

GoodPower 6: From Idea to Global Opportunity

The international journey for GoodPower’s first hybrid project outside the Nordics.

2019 • START

Idea & Feasibility Studies

Project initiation and initial land identification in Southeast Asia.

2025 • COMPLETED

Inquiry & Lease

Inquiry / discussions with EDL regarding grid connection. Lease agreement in place.

2026 • ONGOING

Engineering & Feasibility Study

Drone images and video taken to initiate engineering and feasibility study work.

NEXT STEP • PLANNED

Formal Application

Formal application to be submitted to EDL (Électricité du Laos).

Geographical diversification: First project outside the Nordics.
Technical innovation: Hybrid solution with solar + battery storage.
Large-scale potential: Up to 100 MW solar + 200 MWh battery.

👥 CONTACT

Interested in GoodPower 6?

Contact Project Manager Veeradeth Thamhaksa for more information about our international expansion to Laos.

Veeradeth Thamhaksa

Project Manager
📱 +46 70 69 26 866
📨 GO TO CONTACT PAGE

Explore Our Full Portfolio

GoodPower 6 is part of our larger portfolio. See all our projects and the total capacity we are building.

📊 SEE FULL PROJECT PORTFOLIO