GoodPower 5 (GP5)
10 MW battery storage in Kävlinge. Grid connection with Kraftringen/Skånsk Energi & E.ON. Lease completed 2025. Grid study ongoing. RTB target for Q4 2026–Q1 2027.
GoodPower 5: Path to RTB 2027
Unique project with complex grid connection in Kävlinge – on the path to RTB 2027.
Idea & Feasibility Studies
Project initiation and first site identification.
Inquiry
Inquiry to Kraftringen/Skånsk Energi for grid connection.
Grid Application
Formal grid application to Kraftringen/Skånsk Energi for grid connection.
Grid Study & Lease
Grid study ongoing with E.ON as regional grid operator. Lease agreement in place.
Construction Permit & RTB
Construction permit application Q3 2026. Expected RTB Q4 2026.
Complex grid connection: Collaboration between Kraftringen/Skånsk Energi and E.ON.
With RTB: Follow a project that already has lease and started grid connection – unique position.
All important details in one place
Complete overview of GoodPower 5’s technical parameters and project status
Project & Location
Grid Connection
Land & Permits
Simulation & Data
📰 Project News & Updates
Follow the development of GoodPower 5 in our central news feed. Latest news: Grid connection process ongoing.
📰 View all project newsLatest updates:
- ↻ Grid study ongoing with E.ON
- ✓ Lease agreement in place (2025)
- 🔌 Complex grid connection with Kraftringen & E.ON