GoodPower 1 (GP1)
15 MW / 70 MWh battery storage in Malmö. Construction permit granted 2025-12-01 with RTB target for Q1 2026.
GoodPower 1: From Idea to RTB
Step-by-step process that makes GoodPower 1 our flagship project
Idea & Feasibility Studies
Strategic site identification in Malmö – central in Scandinavia’s energy hub.
Inquiry & Lease
Inquiry to E.ON for grid connection. Lease agreement in place.
Grid Application & Permit
Formal grid application to E.ON. Construction permit granted 2025-12-01.
Grid Study & Pilot
Grid study ongoing with E.ON. Selected as E.ON pilot project.
Connection & RTB
Expected connection agreement Q1 2026. RTB status Q1 2026 – ready for construction.
Traditional development: 4+ years from start to construction permit.
With RTB: Invest directly in a project that already has a granted construction permit – no waiting.
All important details in one place
Complete overview of GoodPower 1’s technical parameters and project status
BESS Technology
Grid Connection
Permits & Status
Revenue Streams
📰 Project News & Updates
Follow the development of GoodPower 1 from construction permit to RTB in our central news feed.
📰 View all project newsLatest updates:
- ✓ Construction permit granted for GoodPower 1 (2025-12-01)
- ↻ Grid study ongoing with E.ON (Pilot Project)
- 📊 AI-based revenue forecast ready for due diligence